
The big day has arrived. Leo and company arrive practically on schedule. On concrete days this is the calm before the potential storm. Usually at this stage nothing can go wrong. Myself, I'm able to walk around, hop here and there and make sure every loose end I can think of has been squared away. With the property starting to take shape I'm more particular about the route the pipe takes getting to the pour. I have no idea how it is in the States but here the concrete pours are really messy.
Every time they break pipe down, put it together, move it etc there are spills. Some get very large. If the spills set in the wrong place, on the wrong things, it is a huge pain in the ass to clean up-some times jack hammer painful. Forget about the pump truck crew cleaning up.
With all that stated, I direct where I want the pipe to go. Yes sometimes we yell back and forth. I get my way in the end.

As I have previously mentioned I don't pay for the crew until the concrete starts pumping. I'm happy he is enjoying himself. Because of the nature of my pours it can take a couple of hours for the pump truck to set up and lay all the pipe. Sometimes it is almost 200'. Timing is everything and Majestic has been known to send trucks early to get them on the road. On several
occasions that has led to backed upped trucks pumping very hot concrete.

We built a similar ramp on the lower cistern. I cannot say enough about them.
Because of a host of reasons, chief among them the difficulty of getting trucks up here, I tend to have complicated pours. I tell Leo or Jeff, as the case may be, what I want done and then we figure out how to do it. As we have in the past, on other projects, I formed up the septic and lower cistern such that we could pour the slabs and walls on the same day. Yup, this definitely runs the risk of problems but I roll the dice. I figure the risk is worth the concrete loss should something happen. The difficulty of getting a pumper up the hill, the spotty availability of concrete and the cooperation of the weather make me more of a gambler than I already am--that takes some doing! I certainly would not take the same risk with the house. Never. The loss would be too great.
All that said, on this pour we are going to pour the slab of the septic first, jump over and do the lower cistern. If I have my yardage right we will get a break to change trucks after the lower slab is done. It will give it time to set up before we pour the walls. Finger crossed with the dice rolling.

The sluice we built for Jeff.
Even though we did not really use it, it made things a lot easier bringing down the pipe. The sluice was old 6" waste pipe that I cut in half. It was from one of Roger's properties. When he started some construction I jumped in and grabbed it.
Like most of the concrete I get, it is pretty stiff by the time it makes it from Cruz bay. Don't get me wrong I would prefer that to runny concrete but it makes it harder to move around. That's where Thor comes in! You saw the pictures of him. He likes it stiff. It keeps him in shape. He is a sick man. Without him this pour would have been a failure. Jeff, who passed on this job, is the only other person I know that moves as much concrete. I get tired watching.
The crew I paid for was okay. But when it gets really heavy there's only a VERY few folks that can get it done. To be honest I have no idea if I could have done it when I was 35. Sure I would have lasted longer than the 20 minutes I do now without a break, but hours, I'm not sure. Just try to imagine standing practically knee deep in five yards of hot concrete that is not self spreading. Your job is to spread it around a 8x12' area by the shovel full, knowing that it is getting stiffer and stiffer as you work. You have 30 minutes. Plus you have to get it reasonably level. Me, I'm good for about fifteen minutes, max! It is heart thumping work with a small dose of panic. I'm like Redd Fox on Sanford and Son having a heart attack all the time. Thor gets it done. The crew I paid for jumps down, puts up elevated planks and proceeds to level the slab.
They switch trucks. We have used eight yards for the two slabs. Meanwhile Thor jumps over the wall and starts leveling the exterior slab of the cistern. Same drill as the inside but even stiffer now. Every shovel full moved now is jack hammer work that won't have to be done busting out the wall forms. Don't forget we are pouring the slab and walls at the same time. Me, I'm getting CPR as I watch.
With a new truck in the saddle they start pouring the walls. The slab holds, the rotted re-enforced plywood forms and termite pitted 2x4's, doubled up for luck, do their job.
Imagine. There are tourists, usually from cities, who are afraid of lizards! Without lizards humans could not live in the tropics.
The cistern walls took another truck and a half. We get a break while they change to the new truck. NO BLOWOUTS!!!!! You can't imagine the relief.

With the cistern completed they break the pipe down to pour the slab and pool. I want this to be one
contiguous pour for a host of reasons, strength being one of them. The plan is to start in the back corner and work forward
screeding as we go and in one final move pour the walls of the pool. See that mess above. That is what happens when you break downhill pipe apart to move it. The concrete above the break leaks out everywhere. In this particular case something happened, who knows what, and we had nearly 1/2 a yard spill out. You can see the stain on the patio. This is the one time I had to yell at the crew to pick up shovels and clean the deck. They really enjoy watching me and Thor. Well, mostly Thor!
.JPG)
The back corner of the patio is out the door on the left.
The back corner we started in. So far so good. The crew Leo brought were pretty good with their trowel work. Not quite tile ready but pretty close given the circumstances. They relaid the pipe back to the septic and put another truck load in there. By this time we were around 32 yards.
Then the rain came. Murphy's law.
It wasn't a particularly heavy rain. Hard and short. But enough so that the empty truck could not get down the mountain and the full one could not get up. The empty truck could not even get up the
cul duc sac. Meanwhile Leo and crew did nothing. The key word is nothing. This is the second time with Leo that it rained and he did nothing. Nothing, you ask? There's concrete in his pipe, 4" pipe no less. It starts to set, just like it did last time. Set? Yeah, it won't come out on its own. I ask him why isn't he
squeezing out a few inches every ten minutes or so. Blah, blah, blah.
Of course it gets stiffer. Like last time, the solution is to take apart the entire run, each ten foot piece, and pound it out with baby sledges.
Like I said, I don't pay when the concrete doesn't pump. Now you know another reason why!

The rain stops. The road dries and trucks move.

At least some one is happy. Pink
flamingos, a very rare
sighting on St John.

Well they finally get the pipes cleared and move everything to the upper deck. The area to be poured is on the left where the
rebar sits. The far corner is the exterior shower. You can see the white plumbing PVC sticking up.
We have three main pours left. The patio slab, the upper four foot driveway retaining wall and the new lower driveway. Once again because of the rain and more importantly the pipe delay, well over an hour, we are not going to complete the pour. It will be dark. I cancel the last eight yards. I went into this job owed six yards and I'm coming out owed eight!
They had to add a lot of water to the last truck. It was not
Majestic's fault their truck sat so long. It was Leo's. I don't really care at this point. It's just the upper patio that will end up under 1/2"
travertine. In fact it was nice to work with self leveling concrete for once. The deck and shower are tile ready!

Leo ran his usual trip on me. Always with a smile. In Leo's world the pipe delay is just life. Because he likes me he'll gladly come back tomorrow to finish the job. Oh really? Problem is, in Leo's world, tomorrow is a new day and a new CHARGE. Just like last time I got shorted with his pipe snafu, thanks but no thanks.

It's a crying game as my bud Jim says.
As always I make my pours as big as I can. Next time will be the roof for the septic, finish all the retaining walls raising the driveway, steps and a new three inch floor on the lower interior level to take out a pretty significant swale that happened on the original pour when the house slab was poured.
Leo clicks into plan B. Figuring out the charges.
I already wrote the check. I handed it to him before he did his math. "But, but, but." I said no Leo, I spoke to your uncle days ago. I get 100' of pipe and 20 yards for your show up fee. After that I pay $10 for every extra 20' of pipe and $10 for every extra yard. We poured forty yards, here's the money for the crew for the time the concrete was FLOWING. Here's $100 for you for showing up on short notice. I tell him to clean his truck out on my driveway. I spread it. With all the water almost another yard comes out of the pumper. At least I have a concrete turn to the lower packed driveway now.
After paying Thor, its another two grand pumping day with another $10,400 in concrete. Welcome to paradise!
Thor is leaving this time on a 98' footer. Computerized helm. Hmmm. I guess at those prices they can't risk a human error at the helm. I would sure love to sail something that big in some weather. I'll head home in ten days or so. I never make reservations before a pour. I only end up canceling them.
I'm going to the beach, a place I don't get to very often.
Thanks for the updates. Keep up the good work.
ReplyDelete